The installation method of bamboo and wood fiber wallboard mainly includes the following steps:
- Preparation
Tools: Prepare all required tools, such as screwdrivers, electric drills, rulers, pencils, cutting machines, utility knives, structural glue guns, levels, Angle grinders, square feet, tape measures, and triangle files.
Materials: Ensure that bamboo and wood fiberboard, self-tapping nails, glue (structural glue is recommended to ensure the fixing effect), keel (horizontal and vertical), wood square (used for the top of the light belt structure), woodworking board (used for the background wall or the bottom of the ceiling) and other materials are available.
Site preparation: Clean the construction site, ensure that the wall is clean and tidy, and no debris will affect the construction effect. - Measurement and cutting
Measurement size: According to the design drawing and actual size, use a ruler and pencil to measure on the wall to determine the size and position of bamboo and wood fiberboard.
Cutting sheet: Use the cutting machine to cut along the measured lines to ensure that the incision is neat and smooth. Pay attention to safety during the cutting process to avoid injury.
Third, install the keel and fasteners
Fixed transverse keel: fixed transverse keel on the wall, keel spacing is generally 500mm~600mm, according to the actual situation to adjust.
Fixed vertical keel: fixed vertical keel on the horizontal keel, vertical keel spacing is generally 300mm~400mm, also adjusted according to the actual situation. Note that the vertical keel is perpendicular to the horizontal keel.
Use self-tapping nails to fix: Use self-tapping nails to firmly fix the horizontal keel and vertical keel on the wall.
Four, installation of bamboo and wood fiberboard
Place the board: Place the already cut bamboo and wood fiberboard on the keel, ensuring that the joint between the board and the keel is tight.
Drilling and fixing: Use an electric drill to drill holes at the edge of the bamboo and wood fiberboard, and then insert self-tapping nails to fix. Be careful not to damage the surface of the plate when punching.
Repeat installation: Follow the above steps to install the remaining bamboo and wood fiberboard on the wall one by one. - Inspection and repair
Check the flatness: After the installation is completed, carefully check whether the bamboo and wood fiberboard is smooth, if there is warping phenomenon, repair in time.
Check the joint: Check whether the joint between the bamboo and wood fiberboard and the wall is tight, if there is loosening, it should also be repaired in time. - Cleaning and protection
Clean up the site: After the construction is completed, clean up the construction site and keep the wall clean.
Protection treatment: Protection treatment of bamboo and wood fiberboard, such as applying waterproof paint or covering protective film, to extend the service life.
In addition, the following points need to be noted during the installation process:
Installation sequence: It is usually recommended to install the ceiling first and then the wall, install the main plate first and then install the line, install the large area first and then deal with the details such as corner and edge.
Socket reservation: If you encounter the socket location, you need to reserve the socket port in advance.
Detail treatment: In the details of bending, splicing, etc., to ensure that the right Angle is neat and the splicing is tight.
Following the above steps and precautions can ensure the installation quality and beauty of bamboo and wood fiber wallboard.